A six-month world's fair in 1968 drew 6.3 million visitors, lost $7.5 million and left a tower, a convention center and a park.

The gates opened April 6, 1968, and closed October 6. In those six months HemisFair '68, an official international exposition, drew about 6.3 million visitors to a site of roughly 96 acres just south of downtown San Antonio. Its theme was "The Confluence of Civilizations in the Americas." More than thirty nations and fifteen corporations hosted pavilions, and the Bureau International des Expositions had granted the fair official status on November 17, 1965. Attendance fell short of what the planners predicted. The fair lost $7.5 million.

Almost sixty years on, the fair is still the largest single act of urban planning in the middle of San Antonio, and what it left is visible from nearly every high place in the city: the tower, the convention center, the courthouse that began as a federal pavilion and a park whose name was changed in 2015. Here are the numbers, the site and what the fair left behind.

The money

The announced cost was $156 million. The public share, as a reference history of the fair itemizes it, came in five pieces:

Source Amount Purpose
U.S. Housing and Home Finance Agency $12.2 million acquiring and clearing the site
City bonds $11 million convention center and arena
City general revenues $5.5 million Tower of the Americas
State of Texas $10 million Texas pavilion
Congress $7.5 million U.S. pavilion

Add the five lines and the total is $46.2 million, about 30 percent of the $156 million announced cost (46.2 divided by 156 is 0.296). The rest came from other sources, corporate sponsors and ticket revenue among them. The $7.5 million loss was about 4.8 percent of the announced cost.

Set attendance against the calendar. April 6 to October 6 is 183 days, and 6.3 million visitors over 183 days averages about 34,000 a day. Attendance never matched the predictions, and the predicted figure itself is the number history leaves loose, so the size of the shortfall is anyone's guess. What is certain is that the fair finished $7.5 million in the red.

Five dates that frame the fair

A fair this large takes years to set up, and the dates show the sequence.

  1. May 27, 1965. The Texas Legislature establishes the facility that becomes the State of Texas Pavilion and, later, the Institute of Texan Cultures.
  2. November 17, 1965. The Bureau International des Expositions grants HemisFair official fair status.
  3. August 9, 1966. The agreement with preservation interests saves 20 existing structures on the site, with 24 saved in total by the end.
  4. April 6, 1968. The fair opens.
  5. October 6, 1968. The fair closes after 183 days.

Less than three years separate the first date from the fourth. That is not much time to acquire and clear 96 acres, design a tower and several pavilions and pay for all of it, and the schedule explains why preservation was negotiated under pressure. The fair had a hard opening date, and the clearing had to be done before it.

The site and what was cleared

The fair's land was acquired mainly through eminent domain, and many structures were demolished or moved. Residents still talk about that part of the story, and the record tells only a piece of it. The reference history says the San Antonio Conservation Society recommended preserving 129 structures. An agreement dated August 9, 1966, saved only 20 existing structures, and 24 were saved in the end. A total count of homes and buildings cleared is a figure to look for in the city's archives.

The Conservation Society's part deserves notice. The organization was formed in 1924, and its history is covered in The San Antonio Conservation Society, 1924 to today. By the time of the fair it was a veteran of preservation fights, and a negotiated outcome that saved 24 of the 129 structures it asked for is a mixed result however you read it: a victory for the structures that remain and a loss for those that do not.

The trade can be read two ways. One reading holds that clearing the site was the price of a project that brought national funding and a world's fair to a mid-sized city. The other holds that the loss of neighborhood buildings was too high. The documented facts bearing on both are the federal funding of site clearance, the use of eminent domain and the 24 structures saved.

The Tower of the Americas

The fair's theme structure was the Tower of the Americas. The reference history gives its height as 750 feet and calls it San Antonio's tallest structure, designed by the architect O'Neil Ford. The city paid for it with $5.5 million in general revenues. It was built for the fair and has outlasted nearly everything else built for it. Its story from the observation deck is told in The Tower of the Americas, built for a world's fair.

For downtown, the tower supplied a skyline marker visible from much of the central city, a fixed point for giving directions.

The pavilions: three survivors and one loss

The two largest buildings of the fair had very different afterlives.

The Texas pavilion became the Institute of Texan Cultures. The Texas Legislature established the institute on May 27, 1965. It first served as the State of Texas Pavilion at HemisFair, the largest pavilion at the fair. The University of Texas System took it over in 1969, UTSA gained administrative control in 1973, and it was designated a UTSA campus in 1986. It hosted the annual Texas Folklife Festival, held since 1972. The brutalist building was listed on the National Register of Historic Places in 2024. According to a reference summary updated in July 2025, UTSA announced that the museum would cease operations on May 31, 2024, and demolition began on April 8, 2025, despite lawsuits to stop it, to make way for a sports and entertainment complex known as Project Marvel. The Spurs arena that complex refers to is covered in The new Spurs arena and Proposition B. The institute's collections and its planned temporary and permanent homes are for the institute and UTSA to announce.

The U.S. pavilion became a courthouse. The United States Confluence Theater is now the John H. Wood, Jr. federal courthouse, and the Confluence Exhibit Hall is now the Adrian Spears Judicial Training Center. The fountain called Migration is still outlined on the site, though bushes replaced its bird sculptures.

The convention center and arena. The Convention Center Theater, now the Lila Cockrell Theater, was one of three buildings built with the convention center and arena. A $26 million renovation of the theater followed in 2010. The city owns about 50 acres of the site, and the Henry B. Gonzalez Convention Center occupies 30 of them. The tax that funds expansion of that convention center is explained in tourism jobs and the hotel tax.

The decades after

Most fairs leave a hole when they close, and this one was no exception. Unused fair structures were removed in 1986, and about 15 acres were redeveloped for the fair's twentieth anniversary. In April 1988 the site was rededicated as HemisFair Park.

The slower rebuilding came later. In 2008 Hyatt completed the Grand Hyatt San Antonio on the north and east sides of the convention center. In 2009 the City Council created the HemisFair Park Area Redevelopment Corporation under Mayor Julián Castro. In 2012 the corporation renovated three structures and the council approved a master plan calling for three parks: Yanaguana Garden, Civic Park and Tower Park. In 2015 the council unanimously approved renaming the area simply "Hemisfair," and Yanaguana Garden opened on October 2, 2015.

The timeline shows how long it takes to turn a cleared site into a neighborhood: eighteen years from the fair's end in 1968 to the first major clearance of leftover structures in 1986, and another twenty-nine to the garden's opening in 2015.

Reading the fair today

A few ways to see what remains.

  1. Walk the park. The 2015 garden and the grounds around the tower are public. The HemisFair record details what is where.
  2. Stand under the tower and look at the buildings. The courthouse, the convention center and the arena complex sit on the pavilion sites. Picture them as exhibition halls in 1968.
  3. Notice the edges. Where the fair site meets La Villita and the River Walk, the line between preserved and cleared land shows in building styles and street patterns.
  4. Follow the paper trail. The city's Planning Department and its Office of Historic Preservation, described in Planning Department and Office of Historic Preservation, hold records of what was designated and what was planned. Hemisfair itself is one of the 32 local historic districts on the City's list.

For the district's story after the fair, see HemisFair after 1968: what the world's fair left downtown.

What it did to the downtown

One lasting effect of HemisFair is that the area south of the downtown core gained a convention center, a tower and, later, a large hotel beside the convention center, which gave the visitor economy that tourism jobs and the hotel tax describes a physical frame. The fair did not create San Antonio's tourism, which had roots in the Alamo and the River Walk. It gave tourism infrastructure at scale.

It also set a pattern of large public projects in the city center, decided by public bodies and paid for in part with outside money. The pattern shows in later ballot measures and arena deals. The 1968 version had federal money for clearance, city bonds for buildings and state and congressional money for pavilions. Whether that model produced a good outcome depends on what one counts. The buildings, the tower and the park are the evidence on one side, and the 129 structures the Conservation Society asked to save, of which 24 were, are the evidence on the other.