The Alamo Plan, a museum, a plaza and a 2028 target
A $550 million plan, with $400 million from the state, is building a museum in two old downtown buildings. The pieces, the numbers and the 2028 target.
Ask a San Antonian what the Alamo is right now and you may hear "a hole in the ground with a fence around it." The place has spent most of a decade as a construction site, a fundraising campaign and a running argument over how a shrine that millions of people visit ought to be arranged. The effort goes by the Alamo Plan. Its centerpiece, a visitor center and museum, is now reported to open in 2028, later than earlier announcements promised.
What follows is what the plan consists of, how it is paid for, what its backers project and what is still unsettled. The figures come from the plan's published materials and public reporting, and each carries a date, because they have moved more than once.
Where the plan came from
The structure of the plan makes sense only against the Alamo's recent management history. In 2011 the Texas Legislature took authority over the Alamo away from the Daughters of the Republic of Texas and gave it to the Texas General Land Office. In 2015 the GLO ended the Daughters' contract, and a new management organization, Alamo Complex Management, later called the Alamo Trust, took over the daily running of the place. The state owns the site. The longer account is in The Alamo after 1836, from Army depot to church sale to state ownership.
In 2017 the General Land Office, the Alamo Endowment and the City of San Antonio unveiled a joint master plan. In 2020 the Texas Historical Commission voted to leave the Alamo Cenotaph where it stands. The long barrack reopened in October 2021. Those are the steps that turned a master plan into a funded project.
What the plan includes
A June 2025 report on the project lists these components:
- Restoring the original footprint. The plan seeks to bring back the Alamo's original four-and-a-half-acre footprint.
- A Visitor Center and Museum. About 160,000 square feet, with more than 5,000 artifacts in eight galleries. The report lists a 4D theater, a 700-person event space and a terrace overlooking the church. The museum takes over two existing buildings: the Crockett Block, built in 1882, and the Woolworth Building, built in 1921.
- The Texas Cavaliers Education Center.
- A pedestrian mall.
The two old buildings deserve a second look. Nobody is putting a museum on a vacant lot. The plan reuses downtown buildings that already belong to the plaza's history, which keeps the museum on the plaza and stitches old construction to new.
Some arithmetic gives a feel for the size, with a warning attached. Spread 160,000 square feet evenly across eight galleries and each averages 20,000 square feet; spread 5,000 artifacts the same way and each gallery holds about 625. Neither number is real. The building also holds a theater, an event space, a terrace and the usual lobbies, stairs and storage, so galleries are only part of the total, and objects are never spread evenly. The sums show an order of magnitude and no more.
Work already done
The same report lists what is finished: the Ralston Family Collections Center, on March 3, 2023, and the Mission Gate and Lunette, on May 10, 2024. A promenade was scheduled to open in November 2025, and the Texas Cavaliers Education Center on March 6, 2026. Restoration of the church building was scheduled to begin in spring 2027. These dates come from a 2025 report, so read them as plans and confirm on the Alamo Trust's current project page what has actually opened.
The plan at a glance
| Date | Step |
|---|---|
| 2011 | State law moves authority to the General Land Office |
| 2015 | GLO ends the Daughters contract; management passes to the Alamo Complex Management organization, later the Alamo Trust |
| 2017 | GLO, Alamo Endowment and the city unveil a joint master plan |
| 2020 | Texas Historical Commission votes to keep the Cenotaph in place |
| October 2021 | The long barrack reopens |
| March 3, 2023 | Ralston Family Collections Center completed |
| May 10, 2024 | Mission Gate and Lunette completed |
| Late 2025 and early 2026 | Promenade and Texas Cavaliers Education Center scheduled to open, per the 2025 report |
| Spring 2027 | Church restoration scheduled to begin, per the same report |
| 2028 | Reported target for the museum's opening |
Read top to bottom, the table covers about a decade and a half: governance fights first, then planning, then construction, and the job still not finished. Anything dated after 2024 should be checked against current announcements.
The money
The plan's total cost is reported at $550 million. The report breaks the funding down this way:
| Source | Amount |
|---|---|
| State of Texas appropriation | $400 million |
| Remaining to raise | $150 million |
| Raised by the Alamo Trust (as of mid-2025) | close to $90 million |
The arithmetic is simple. Take $400 million from $550 million and $150 million is left. If close to $90 million of it had been raised by mid-2025, about $60 million was still to find (150 minus 90). That estimate rests on a report more than a year old, so ask the Alamo Trust for a current number.
An earlier account of the master plan put the proposed cost at $450 million for a museum of about 100,000 square feet. Against the later figures of $550 million and 160,000 square feet, the plan grew by $100 million and 60,000 square feet. That is the sort of detail to check in the primary documents, since a reported cost is only as good as the date attached to it.
What the backers project
The same report carries projections, and it names who makes them. The state projects a 56 percent increase in tourism at the Alamo. The Alamo Trust's economic studies put the total economic benefit at $11.3 billion over the first five years after the museum opens. Annual visitors are expected to climb from 1.6 million to 2.5 million once the renovations are done.
Check the first against the third: 2.5 divided by 1.6 is 1.5625, a 56 percent increase. The two figures describe the same projection.
A projection is a forecast and not a result. The $11.3 billion is the Alamo Trust's own estimate, and independent economists might weigh the same inputs differently. Treat all of it as the backers' case, and say so when you repeat it.
The timeline and the slip
Reports before 2025 pointed to a 2026 opening. The June 2025 report left the Visitor Center and Museum opening to be determined, with full project completion estimated for 2027. Later reports say 2028. Big construction jobs slip for plenty of reasons, among them design, supply, weather and money, and the Alamo Trust's announcements are where a change in date gets explained.
The practical consequence is plain enough: do not plan a trip around a museum that may not be open. The grounds and the church remain the main draw while the work goes on. For visiting information, see Visiting the Alamo: what to know while the Alamo Plan is under construction.
Notice how many of the items above are described as dated or scheduled. Plans like this shift as the work moves, so before repeating any date here, check it against the Alamo Trust's current announcements.
The questions people ask
A project this size draws questions from supporters and skeptics alike. These are the ones the public record can answer without taking a side.
Who pays? The state's $400 million is the largest piece. The rest depends on private fundraising by the Alamo Trust. The city is a partner in the master plan, and its budget documents, described in How to read the San Antonio city budget, are where any city dollar figure would show up.
Who owns and runs it? The state owns the site, the General Land Office holds custody and the Alamo Trust manages daily operations.
How does the plan square with the World Heritage listing? The Alamo belongs to the San Antonio Missions World Heritage Site, inscribed in 2015. A project that changes the setting of a listed site will have its design watched. What the listing does and does not require is covered in What UNESCO recognition means for the missions and the Alamo.
What does it do to downtown? The Alamo sits in the middle of downtown, a short walk from the river and the neighborhood described in Downtown San Antonio. Construction changes the pedestrian routes, and the plan's pedestrian mall would change how people move around the plaza afterward. The city's preservation office, described in Office of Historic Preservation, and the local historic district rules covering Alamo Plaza are part of the review framework, and review of the plan runs through them.
Will it be worth the cost? That turns on the projections above and on what you measure. A visitor count of 2.5 million is a forecast. The first years after opening will supply the answer.
Following the project
Three habits for staying current:
- Check the Alamo Trust's project page for finished pieces and the opening date.
- Read state and city documents. The Texas General Land Office and the City of San Antonio publish project information. The city's budget and council records, see Inside the $4.41 billion FY 2027 budget and A Thursday A Session, item by item, would show any city action.
- Put a date on every figure. On this project costs, square footage and opening dates have all changed, and a number with no date is hard to use.
The city's other long projects, from the airport terminal to the Silver Line, follow the same pattern of figures that change with time. The Alamo Plan stands apart for the weight of the ground: a shrine that draws visitors from around the world, in the middle of a modern downtown, being rebuilt around a story more than three centuries old.