The San Antonio Missions are leaving Nelson Wolff Stadium for a roughly $160 million downtown ballpark by San Pedro Creek, targeted for April 2029.

Thirty years on the West Side, and the San Antonio Missions are packing. Since 1994 home has been Nelson Wolff Stadium, room for about 9,200 fans, a Double-A team in the Texas League and, at present, an affiliate of the San Diego Padres. The plan is to leave. The new home will be a downtown ballpark at Camaron and North Flores Streets, beside San Pedro Creek, at a cost of roughly $160 million.

The plan has moved forward in steps, and its timeline has moved back. A report in September 2026 put opening day in April 2029; earlier reports had said 2028. Here is what is known about the deal as of November 2026, in the form of the questions a resident might ask.

What is the plan?

A new baseball stadium on the edge of downtown, on a site beside San Pedro Creek at Camaron and North Flores Streets. The team would not own the ballpark. A public body would, the San Pedro Creek Development Authority, formed by the city and the county. The team's owners, Designated Builders LLC, are contributing $34 million toward the cost, and the rest is public money in a structure worked out between the county and the city. The county's April 2026 deal to finance the ballpark was reported under a headline noting that it also "gets a park too," a nod to public space in the package.

The ballpark is one part of something larger. The private developer Weston Urban plans an apartment and hotel district around it, with a first tower of 27 stories and 681 residential units. In effect the ballpark anchors a mixed-use neighborhood, which is how its backers describe it: a baseball stadium that is also a way to put activity on land that sits close to downtown but has not drawn much.

Why move at all?

Nelson Wolff Stadium has been the team's home since 1994 and sits on the West Side, away from the central city. The new site is downtown, near the river and the existing visitor economy, and a downtown location lets a team draw office workers and visitors as well as families who drive to a game. The case for moving rests on location and the visitor economy, not on any finding that the old stadium failed a standard. What the reports do show is that the county and the team reached a deal to build a new ballpark.

Who pays?

The split of the roughly $160 million cost, as reported, has these parts:

  • The team's owners: $34 million.
  • Public money: the balance, structured through the San Pedro Creek Development Authority, a body formed by the city and the county. Reports on the county's April 2026 financing deal describe the county's role, and the details of the bond or lease structure are in the county's public documents.

Do the division: $34 million is 21 percent of $160 million (34 divided by 160 is 0.2125), so if the balance is public money, as the reports describe, the public share is roughly four-fifths. That is a rough figure, because the total cost has been described as "roughly" $160 million and the exact accounting of public and private shares depends on what counts as part of the project; the park, the infrastructure and the private housing are separate.

The comparison with the arena votes of November 2025 is instructive. The Spurs arena measure directed up to $311 million of the county venue tax toward a downtown arena, with the team pledging at least $500 million and the city about $489 million, and it needed voter approval (see The new Spurs arena and Proposition B). The ballpark deal was reported as an agreement among public bodies and the team, not a ballot measure. How the two projects relate to the same venue tax is explained in how hotel and car-rental taxes fund arenas.

The venues, side by side

The ballpark joins a short list of large public-assembly venues in the city. Capacities are approximate and come from the figures the city's other pieces use; sources differ on the arena, so the figure there is rounded.

Venue Main tenant Approximate capacity
Alamodome (opened 1993) UTSA football about 65,000
Frost Bank Center (since 2002) Spurs about 18,500
Nelson Wolff Stadium (since 1994) Missions about 9,200
Toyota Field San Antonio FC about 8,300

Seating capacity, like the design, settles as the plans firm up, and the team and the county are the ones who publish it.

The 2026 timeline

Most of what is known about the plan comes from three public moments in the second half of the year.

  1. April 30, 2026: Bexar County announces a deal to finance the downtown baseball stadium, reported with the news that the project also adds a park.
  2. July 31, 2026: a report says the season opener at the planned downtown ballpark is delayed to 2029.
  3. September 2026: the city holds public meetings on the future of the Wolff stadium site, and the newest report puts the opening in April 2029.

Between the first and the last, the date moved by roughly a year. For readers tracking a project like this, the most useful habit is to note the date of any figure and to expect revisions.

Baseball in the city's calendar

The Missions are one of several teams that give San Antonio a sports year. The Spurs have been in the city since 1973 and won five NBA titles, in 1999, 2003, 2005, 2007 and 2014; San Antonio FC won the league championship of its division in 2022; UTSA plays football at the Alamodome (see The Spurs: from the Dallas Chaparrals to San Antonio and San Antonio FC at Toyota Field). A downtown ballpark adds a summer venue near the hotels and the river, which is the argument for putting it there. How ticket prices and promotions will change in a new stadium is not something the reports address.

What is the schedule?

It has slipped. Reports before 2026 pointed to an opening in 2028; the report of September 2026 gives opening day as April 2029. A year's delay on a stadium project is not unusual, and it does not by itself signal trouble, but it does mean the 2027 and 2028 seasons are expected to be played at Nelson Wolff Stadium.

Anyone planning around the new ballpark should read the date as a target. Construction schedules shift with permits, financing and weather.

What happens to the old stadium?

The city held public meetings in September 2026 on the future of the Wolff stadium site. The reports announce no decision, and the question has two layers: what the land will become and who will pay for it. Residents who care about the West Side will want to follow those meetings and the council's agendas on the site (see What happens to Nelson Wolff Stadium). A large, well-located site tends to draw more than one proposal, and the process of deciding is public.

What does it mean for the neighborhood?

The site by San Pedro Creek sits at the edge of downtown, near the places the city lists in its downtown and West Side neighborhoods (see Downtown San Antonio and Prospect Hill). The development authority that owns the ballpark was formed by the city and the county, so the project sits inside a corridor public bodies are already managing. For the baseball team, that corridor gives access to downtown crowds. For neighbors, the effects include construction, traffic on game days and the possibility of changing property values.

Nothing in the reports allows a firm prediction about any of those effects. What can be said is that the project is a bet about what draws people downtown, and that supporters and critics disagree about whether sports facilities are the best way to place it.

The arguments

For the move: a downtown ballpark can host more events, draw a wider audience and anchor housing and hotel development on land that has been underused. It gives the team a facility built for its needs, and it keeps the team in San Antonio, which matters if one thinks the city's identity includes its baseball.

Against: public money for a privately operated sports team competes with public needs such as streets, housing and drainage. Critics of stadium deals generally argue the economic benefits are smaller than backers claim. And a project that slips from 2028 to 2029 raises questions about how cost and schedule risk are shared.

Both arguments are familiar from stadium debates in other cities, and both are being made here.

How to follow it

  1. County and city agendas. Public bodies approve contracts at posted meetings (see Bexar County Commissioners Court).
  2. The development authority. The San Pedro Creek Development Authority is the owner of record of the ballpark, and its meetings and documents are public.
  3. Planning. The city's Planning Department handles area plans and zoning questions (see Planning Department).
  4. The team. Season schedules and any change in affiliation are announced by the team, not by the city.
  5. Weather and permits. Delays often come from them, and the schedule is the part of the story most likely to change.

Until then the Missions stay at Nelson Wolff Stadium. The latest report says the new ballpark opens in April 2029, the roughly $160 million project on San Pedro Creek, $34 million from the team's owners and the rest from public sources, with 681 residential units in the first tower beside it. Any of those facts may change, and the date on a report is the best guide to how current it is.