The Loop 1604 North Expansion, segment by segment

TxDOT's 23-mile rebuild of Loop 1604 from Bandera Road to I-35: six segments, their costs and completion years, and the eight I-10 flyover ramps.

Take Loop 1604 across the north side of San Antonio in 2026 and you are driving through a construction zone some 23 miles long. The Texas Department of Transportation calls it the Loop 1604 North Expansion: a rebuild of the loop from State Highway 16, which is Bandera Road, on the west to Interstate 35 on the northeast, cut into six construction segments. The agency's project page puts the total at $1.4 billion and promises a road that goes from four lanes to ten.

Better to follow it as a list than a story, because the pieces start and finish at different times. Below are the six segments, then the interchange at I-10 that has produced the most visible change, and a note on where the public figures part ways.

What is being built

Per the TxDOT project page, the expansion turns Loop 1604 from a four-lane expressway into a ten-lane one. The arithmetic is simple: two added general-purpose lanes in each direction take four lanes to eight, and one high-occupancy-vehicle lane in each direction takes eight to ten. The page says the new general-purpose and HOV lanes are non-toll. It also describes:

  • continuous-flow frontage road intersections replacing the current signalized ones;
  • a five-level direct connect interchange at I-10 in place of the old cloverleaf, with the cloverleaf connectors removed;
  • an upgraded intersection at Blanco Road;
  • continuous sidewalks and bicycle accommodations;
  • water quality protection;
  • all improvements within the existing right of way and easements.

TxDOT also says the project could cut travel times by as much as 80 minutes, a figure the agency attributes to the project as a whole, with no stated route or time of day. Loop 1604 runs about 96 miles around the city, so the 23-mile expansion covers roughly a quarter of the ring (23 divided by 96 is 24 percent). Two rings: Loop 410 and Loop 1604 explains why the outer loop, not the inner one, takes the growth.

The six segments

The TxDOT segments page, as read in November 2026, lists these limits, estimated costs, status and expected completion years.

Segment Limits Estimated cost Status listed Expected completion
1 SH 16 (Bandera Road) to I-10 $181 million Under construction 2026
2 The Loop 1604 and I-10 interchange $463 million Under construction 2028
3 I-10 to US 281 $279 million Under construction 2026
4 US 281 to Redland Road $205 million Under construction 2028
5 Redland Road to Judson Road $169 million Anticipated letting in 2024, estimated start in 2025 2028
6 Judson Road to I-35 $182 million Anticipated letting in 2026, estimated start in late 2026 2029

Add the six estimates and you get $1.479 billion, close to the project page's $1.4 billion headline; the segment page's figures may reflect later estimates than the headline. A reader quoting a number should say which page it came from.

Reading the table with care

Three cautions apply.

  1. Some entries look dated. The status of segments 5 and 6 is given as anticipated lettings in 2024 and 2026 and estimated starts in 2025 and late 2026, and whether those dates were met is something to check on the project page. Treat anything outside "under construction" as an estimate.
  2. Other coverage differs. Earlier reporting gave 2027 as the completion year for segment 4, which began construction in April 2024, and TxDOT's current page gives 2028. Assume the latest agency page controls, and check it.
  3. Segments overlap in time. With segments 1 through 4 all under construction, a driver on the loop may see work zones in two places at once. A segment's completion year is when its work ends, not when the whole loop is finished. The last segment's listed completion year is 2029.

The interchange: eight ramps

Segment 2 is the most complicated and the most visible. The cloverleaf where Loop 1604 meets I-10 near La Cantera is being rebuilt as a five-level interchange, which a Community Impact report describes level by level.

  • Level 1, at the ground. Roundabouts give access to adjacent properties, along with new turnarounds and sidewalks along I-10. The VIA Park and Ride is being modified to fit beneath the interchange.
  • Level 2. The I-10 main lanes, with room reserved for future expansion, plus collector-distributor roads that let local traffic bypass the roundabouts.
  • Level 3. The expanded Loop 1604 main lanes, adding one main lane and one HOV lane in each direction, with an 18.5-foot vertical clearance for large trucks.
  • Levels 4 and 5. Eight flyover ramps providing higher-speed connections between the two highways.

The ramps opened one at a time, which is why the interchange has changed shape again and again in recent years:

When Ramp
December 2024 Eastbound Loop 1604 to westbound I-10
Early June 2025 Westbound I-10 to westbound Loop 1604
August 2025 Westbound Loop 1604 to eastbound I-10
September 2025 Eastbound Loop 1604 to eastbound I-10
October 2025 Westbound I-10 to eastbound Loop 1604
November 2025 Eastbound I-10 to both directions of Loop 1604 (two ramps)
February 2026 (scheduled) Westbound Loop 1604 to westbound I-10

The Community Impact article, published February 4, 2026, said TxDOT would open the eighth and final ramp by 5 a.m. on February 5, 2026, and called the interchange 70 percent complete, with estimated completion in 2027. That article reports the opening as scheduled; it does not confirm that it happened, and the TxDOT segments page now gives 2028 for the interchange segment. The agency's own pages are the place to check.

Ground-level work goes on after the ramps open. Most of what remains at the interchange is lower-level infrastructure, such as roundabouts, turnarounds and sidewalks, which matters to anyone who walks, bikes or uses the Park and Ride.

A short glossary for the project pages

Highway project pages use a vocabulary that is easy to misread. These terms appear in TxDOT's pages for this project, defined as plainly as possible.

  • Letting. The point at which the state accepts bids and awards a construction contract. "Anticipated letting in 2026" means the contract is expected to be awarded that year, not that work is under way.
  • Frontage road. A road alongside the main lanes that gives access to businesses and neighborhoods. The project changes its signalized intersections to a continuous-flow design intended to keep traffic moving.
  • HOV lane. A high-occupancy-vehicle lane for vehicles with more than one occupant. The project adds one in each direction, and TxDOT says it is non-toll.
  • Direct connect. A ramp that links two highways without a stop, in contrast to the cloverleaf's loop ramps, which merge traffic into short weaving sections.
  • Collector-distributor road. A parallel road outside the main lanes that gathers local traffic so it does not weave across through traffic.
  • Right of way. The land the state already owns or holds easements on. TxDOT says all the improvements stay within it, which matters to anyone worried about property takings.

A note on I-35 and the rest of the north side

Loop 1604 is not the only road work on the north side. The Texas Department of Transportation also lists an I-35 project from Loop 410 North to FM 3009, with work scheduled from 2022 to 2027. A driver heading to New Braunfels or Austin from the north side can face work on both roads. The project also belongs to the statewide Texas Clear Lanes initiative, according to TxDOT. The A day trip to New Braunfels piece mentions the I-35 corridor from a visitor's side.

Who lives next to it

The expansion cuts through some of the city's fastest-growing territory. The northwest segment passes near La Cantera and the Dominion, where the commercial and entertainment district around The Rim and the Six Flags Fiesta Texas park sits; the La Cantera and The Dominion record describes it. Near US 281 the loop passes close to Stone Oak, the large master-planned area in the Far North, covered in Stone Oak, and beyond it the segments reach the Redland Road and Judson Road areas toward I-35. Stone Oak and the far north: how master-planned San Antonio grew along Loop 1604 covers how the growth that built those neighborhoods built the congestion the project answers.

The reasoning behind the project is in the numbers of that growth. The Census Bureau estimates San Antonio's population at 1,548,422 on July 1, 2025, up 14,359 from the year before, the third-largest numeric gain in the country. A city adding people at that pace puts pressure on its outer roads, which is the stretch this project rebuilds.

What to do as a driver

  • Check before you go. DriveTexas, at drivetexas.org, shows live traffic, closures and work zones, and TxDOT's San Antonio District can be reached at 210-615-1110. How to check DriveTexas before a San Antonio drive explains how to read it.
  • Subscribe for updates. The project page offers an email and SMS subscription form, a fall 2024 newsletter and an April 2024 information packet, and TxDOT San Antonio posts on Facebook.
  • Expect change. Ramps and lanes have shifted repeatedly, so a route that worked last month may not work this month. Navigation apps update faster than printed advice.
  • Report road problems to the right agency. Loop 1604 is a state highway, so a pothole or a signal problem on it goes to TxDOT, not to the city's 3-1-1 line, which handles city streets. The How to use 311 in San Antonio guide explains what the city covers.

The bottom line

The numbers do not line up neatly, and that is a finding. TxDOT lists $1.4 billion for the whole project and $1.479 billion across segments. It lists the interchange as finishing in 2028 while earlier reporting said 2027. It lists two segments as complete in 2026, two in 2028 and the last in 2029. For a driver, the short version is that the construction is real, the ramps at I-10 are open, and work continues across most of the 23 miles. For a researcher, the lesson is to tie each figure to the page and date it came from.