The Silver Line and what comes after the Green Line
VIA's second Advanced Rapid Transit line cleared environmental review in June 2026 and is planned to start construction in 2027.
The Green Line has not carried a single passenger, and VIA is already drawing the line that will cross it. The Rapid Silver Line, the second route in VIA Metropolitan Transit's Advanced Rapid Transit (ART) system, cleared environmental review in June 2026, and construction is planned to begin in 2027. On the agency's own project page the Silver Line was described in 2026 as 70 percent designed. That is far enough along to sketch a route on a map and start arguing about it, and not far enough to promise a day the first bus rolls.
The decision in front of the city is what the Silver Line is, how it differs from the buses San Antonio already rides, and what a dedicated bus lane costs and returns on a street where people also park, drive and run businesses.
Where the Green Line stands
The Silver Line only makes sense beside the Green Line, so start there. The Rapid Green Line is a north-south route of about 10.35 miles. It runs from the area near San Antonio International Airport down San Pedro Avenue, through downtown, to Steves Avenue near the historic missions, and VIA's plans continue service to the Brooks Transit Center. Ground was broken in June 2025. VIA's project page, last modified in May 2026, targets service in spring 2028, and a June 2026 trade report said April 2028. Construction was active along the corridor's segments in the summer of 2026.
A June 2025 news report put the cost at about $480 million. It named the main funding pieces too: a $268 million federal grant announced in December 2024 and a one-eighth-cent sales tax that VIA begins receiving in 2026. VIA said it would run the line from 4 a.m. to 1 a.m. every day, with buses every 10 minutes on weekdays and every 15 minutes on weekends. Stations would have platform-level boarding, ticket kiosks and buses with extra doors so riders get on and off faster.
That service pattern is the whole idea of the category. ART is less a new vehicle than a new way of treating the bus: its own lane where the street allows, signals that give the bus priority, stations instead of stops, and frequency high enough that nobody needs a timetable. VIA's own description is that it should feel something like commuter rail.
What the Silver Line is
Public planning summaries describe the Silver Line as an east-west route through downtown. One summary has it running between the area around the Frost Bank Center on the east side and the area near Our Lady of the Lake University on the west, ending near General McMullen Drive. The same summary says the line would later be extended at each end, to the Kel-Lac Transit Center on the west and a future Eastside Transit Center on the east, under VIA's broader Better Bus plan. Those extensions are planning intentions, not commitments, and VIA's pages are where to follow them.
The city's facts are firmer on process. The June 2026 environmental clearance means the federal review of the corridor's impacts is finished, the gate a federally supported project has to pass before it can seek construction money. VIA held a community open house about the Silver Line on August 18, 2026, at the Mexican American Unity Council on West Commerce Street, and posted exhibit boards and 70 percent design plans afterward. Construction is planned to begin in 2027. One public summary gives an opening around 2031, a date to treat as a working horizon and not a promise. VIA's project page carries the current schedule.
Why east-west? Look at what San Antonio's transit already does. Primo, VIA's limited-stop bus service, began December 17, 2012, on Fredericksburg Road as Route 100, and was extended to Zarzamora Street in January 2019 and Military Drive in August 2019. Those corridors run out from the center like spokes. The Green Line adds a long north-south spine through the middle. A line across downtown from west to east gives the system its first real crossing, a place where a rider can change from one rapid line to the other without riding to the end of a spoke. More on the first line is in The VIA Rapid Green Line: San Antonio's first advanced rapid transit, and on the older service in primo: the limited-stop bus line that began in 2012.
How the money works
A sales tax pays for VIA, and the shape of that tax changed in 2026. Of San Antonio's 8.25 percent total sales tax, the city's tax summary itemizes 0.625 percent for VIA and 0.25 percent for the Advanced Transportation District (ATD). The Texas Comptroller lists the ATD rate as three-eighths of a cent from January 1, 2026. The difference is one-eighth of a cent, which public summaries tie to the transit plan voters approved in 2020 with about 68 percent support.
That one-eighth cent is what the Green Line report calls VIA's new money in 2026. A cent is easy to read past, so here is the arithmetic. Say a household spends $40,000 a year on goods and services subject to sales tax. One-eighth of a cent per dollar is 0.125 percent, so that household's share of the new money is about $50 a year ($40,000 times 0.00125). Across a metro area of about 2.6 million people, small payments like that add up to a funding stream that can match federal grants. That is the logic of a transit tax: small per person, large in total, tied to specific projects. The longer story of where the tax goes is in Where the transit sales tax goes: VIA, the ATD and Pre-K 4 SA.
What a dedicated lane asks of a street
The honest part of any bus rapid transit debate is the pavement, not the bus. Reading what is public about the Green Line, a few tradeoffs keep coming up, and the Silver Line will face the same ones.
Lane space. A dedicated lane takes a lane that drivers, delivery trucks or parked cars used. Supporters argue that a bus that never sits in traffic is the point of the investment: a bus in its own lane is reliable, and reliability is what makes people choose it. Critics of lane conversion argue that streets are scarce, that a lane given to buses is one taken from everyone else, and that some businesses depend on curb access for deliveries and customers. Both arguments describe real costs. VIA's plans for the Green Line include prioritized signals and dedicated lanes, but a lane mileage has not been made public, so a precise accounting of what drivers give up has to wait.
Construction years. VIA committed to giving residents and merchants at least 30 days' notice before work starts in any segment of the Green Line corridor. The notice recognizes that construction is itself a cost, and that a street under construction can hurt the businesses the finished line is supposed to serve. Silver Line neighbors will look for the same promise in 2027.
The side improvements. The Green Line's package is not only buses. It lists more than 10 pedestrian crossings, upgraded and synchronized signals at more than 30 intersections, more than six miles of new or repaired sidewalks and more than 100 new or replaced storm drains. A rapid line is partly a way to pay for the streetscape. Transit supporters make that argument, and it is a reason some neighbors accept the project. Skeptics answer that a street could be rebuilt without a dedicated bus lane at all, and that is a fair question to put to any project.
Who lives near the station. A station near a neighborhood changes who can reach it and, over time, what gets built nearby. The city's Planning Department includes transit-oriented development in its work, and its Transportation Department handles the street side. Neither can say today what the Silver Line will do to rents near its stations. The experience of other cities is mixed: stations can bring investment and new customers, and they can also raise costs for people already there. San Antonio's housing programs, described in The Affordable Housing Bond and the Strategic Housing Implementation Plan, are the tools the city has to respond.
What is still open
A case like this should end on what is unsettled, since that is where a reader can still act.
- The exact route and stations. At 70 percent design the alignment is drawn but not locked. The exhibit boards VIA published after the August 2026 open house are the document to read.
- The cost. No Silver Line cost has been announced. The Green Line's reported $480 million is the only benchmark, and a different corridor, length and mix of bridges and utilities will produce a different number.
- The opening date. The 2031 figure is a projection. The Green Line's own date slipped from earlier estimates to spring 2028, a reminder that large transit projects move.
- The service plan. Whether the Silver Line will match the Green Line's every-10-minutes weekday pattern has not been announced.
Following along
VIA posts project pages, exhibits and service alerts on its website, and its trip planner shows current routes. City Council agendas go up on SASpeakUp at least 72 hours ahead, and anyone may register to speak. For today's fares and passes, see Riding VIA: fares, passes and transfers. For the agency itself, including its phone number, see VIA Metropolitan Transit. Years before any bus runs, the Silver Line will give every neighborhood along it a chance to say what a rapid line should and should not do to its street.