The VIA Rapid Green Line: San Antonio's first advanced rapid transit
A 10.35-mile corridor from near the airport down San Pedro Avenue to Steves Avenue is under construction.
The biggest transit project in town is not a train. It is a bus line, built the way a rail line is built: a dedicated path, stations, a fixed corridor, all of it walled off from the lanes everyone else drives in. VIA Metropolitan Transit calls it advanced rapid transit, or ART, and the first line, the Green Line, has been under construction since a ceremonial groundbreaking in June 2025. It runs 10.35 miles, and VIA's current target for opening is early 2028.
The route
VIA's project page describes the Green Line as a corridor from near San Antonio International Airport down San Pedro Avenue, through downtown, to Steves Avenue near the historic missions. VIA says service continues past that to the Brooks Transit Center on the South Side. The construction itself runs from Isom Road at the north end to Steves Avenue at the south end, and the line's total length is 10.35 miles.
Along the way it touches several places this blog has written about:
- The airport, covered in A passenger's guide to San Antonio International's two terminals and The new terminal at San Antonio International: cost, gates and 2028. The line begins near it, but the page says "near," so a rider should not count on a stop inside a terminal.
- San Pedro Avenue, the street the line follows south from the airport area.
- Downtown, where the line passes through.
- Steves Avenue and the missions area, at the southern end of the construction.
- Brooks, the South Side redevelopment described in The South Side and the Brooks redevelopment, where VIA's transit center is the main transfer point for the VIA Link Southeast zone.
For a visitor, the airport-to-downtown link will likely be the headline use once the line opens. For a South Side resident, the connection from the missions area and Brooks to downtown may matter more. From SAT to downtown: driving, bus or the future Green Line compares the current ways to get from the airport to downtown.
What "advanced rapid transit" means
The term is VIA's, and the page names the Green Line as the region's first ART line. The idea is a bus line that borrows from rail: a distinct corridor, stations that are more than a pole and a sign, and a schedule frequent enough that riders do not need to look it up. Local coverage of the construction describes rapid, dedicated bus lanes.
The Green Line is part of the voter-approved Keep San Antonio Moving plan, according to VIA. Its service plan, as stated on the project's website:
- Hours: 21 hours a day, from 4 a.m. to 1 a.m.
- Weekday frequency: every 10 minutes.
- Weekend frequency: every 15 minutes.
A rough count shows what that means. If a bus ran every 10 minutes through all 21 hours, a stop would see about 126 buses a day in each direction (21 hours times six an hour). At every 15 minutes, a weekend stop would see about 84 (21 times four). The 10-minute frequency may not hold all through the service day, so treat these as upper bounds from the stated frequency. They still tell you something: the line is meant to run often enough that a rider can walk up to a station without checking a timetable.
The dates, and why they conflict
When does it open? The honest answer is "around 2028," with the details depending on who is asked.
| Source | Date given |
|---|---|
| VIA's Keep San Antonio Moving site | Early 2028 |
| VIA's project page, last modified May 16, 2026 | Spring 2028 |
| A June 2026 trade article | April 2028 |
These do not so much contradict as round differently. "Early 2028," "spring 2028" and "April 2028" all point at the first months of 2028, and what changes is how firmly the source will commit. The most careful statement is that VIA targets an opening in early 2028 and that the date is a target, not a promise. A project this size can slip, and the usual cause is not one event but the pile-up of utility work, weather and the sequencing of segments.
Other dates are firmer because they are behind us. The ceremonial groundbreaking at Roosevelt Park on the southern portion of the corridor happened in June 2025. Construction began in earnest with utility relocation and grade-level preparation. The first work was near U.S. Highway 281 and Isom Road in the north, and near Roosevelt and Steves Avenues in the south. As of August 2026, construction was active across segments 1 through 8 of the corridor.
VIA says it builds in phases and gives at least 30 days' notice before each segment begins. For businesses and residents on the route, that notice period is the practical tool for planning around closures. Anyone who lives or works along San Pedro Avenue should watch VIA's notices and service alerts, at viainfo.net, and the city's 3-1-1 line can take reports about street conditions near construction.
How it is paid for
The Green Line's money comes from several streams, and the sales tax is the one a resident sees at the register. VIA says the project is partly funded by a one-eighth-cent sales tax that VIA begins receiving in 2026. Separately, the city's tax summary lists 0.625 percent of the 8.25 percent sales tax as going to VIA.
The pieces of the sales tax are described unevenly. The city's tax summary itemizes 6.25 percent for the state, 1.000 percent for the city, 0.125 percent for Pre-K 4 SA, 0.250 percent for the Advanced Transportation District and 0.625 percent for VIA, totaling 8.25 percent. The Texas Comptroller, though, lists the Advanced Transportation District rate as three-eighths of a percent effective January 1, 2026. The two summaries differ on the split, and the Comptroller's date shows the split changed in 2026; the total stayed 8.25 percent. Where the transit sales tax goes: VIA, the ATD and Pre-K 4 SA and where each cent of the 8.25 percent sales tax goes explain the pieces. The safe statement is that VIA receives a one-eighth-cent addition beginning in 2026 and that part of the Green Line's cost comes from it.
The total cost and any federal grants are set out in VIA's project documents, and a reader who wants the full financing picture should start with VIA's Green Line page.
Where it fits in the system
The Green Line did not appear out of nowhere. VIA's earlier rapid service, the Primo bus rapid transit line, began running in 2012, and primo: the limited-stop bus line that began in 2012 explains where it sits between local bus and the Green Line. The on-demand VIA Link service, described in VIA Link: on-demand rides in six zones, gathers riders from the edges and feeds them to transfer points. The Green Line adds a high-frequency spine.
Then comes the Silver Line, the second ART corridor. It cleared environmental review in June 2026, and construction is planned to begin in 2027. The Silver Line and what comes after the Green Line covers it and the tradeoffs of dedicated bus lanes. In short, the Green Line is the first piece of a plan, not the whole of one.
The system-wide fare structure applies to riders: a regular bus fare is $1.30, with free transfers valid for 2.5 hours, and the pass prices and reduced fares are in VIA fares in 2026: what a ride, a day and a month cost. Whether the Green Line carries a separate fare is a question for VIA, and a rider should check before assuming.
What it asks of the street
A dedicated corridor changes a street. Lanes general traffic uses go to buses, stations are built at the curb or in the median, and intersections are rebuilt to give buses priority or to protect people crossing to a station. That is why this is a street project and not only a transit project.
The city's role is the Transportation Department's Vision Zero and Complete Streets work. Vision Zero in San Antonio: safe streets, Safe Routes and Complete Streets explains the city's approach to safer street design, and a corridor like San Pedro Avenue, where people will walk to stations at all hours, is a natural place for those principles to apply. The city does not describe a formal link between those programs and the Green Line, so the connection here is one of principle, not of record.
For people who drive, the effect shows up in changes to lanes, turning movements and parking, during construction and afterward. Check with VIA before planning a route through an active segment.
For businesses and residents along the route
The notice rule is the most useful fact for anyone who lives or works on the corridor. Because VIA builds in phases and gives at least 30 days' notice before each segment, a business can plan deliveries, parking and staffing around each stage and does not have to guess. Utility relocation and grade-level preparation come first, so the earliest sign of work on a given block will be crews moving pipes and wires, not anything that looks like a station. A resident who wants to report a problem with a street near the work, such as a damaged sidewalk or a broken signal, can still use 3-1-1.
Using this information
A few practical points for a rider:
- The line is not open. Construction is under way, and the target is early 2028.
- Watch for notices. VIA says it gives at least 30 days' notice before each segment starts.
- Check the service plan before 2028. The hours (4 a.m. to 1 a.m.) and frequencies (10 and 15 minutes) are the plan, and they may be refined before opening.
- Use the current system now. Riding VIA: fares, passes and transfers and Getting from San Antonio International Airport to downtown cover riding VIA today.
The Green Line shows how a city commits to a decision over time: a vote on a plan, a sales tax, a groundbreaking in 2025, active construction in 2026 and a target in 2028. Each step is dated, and the last is the one still open.