Ask anyone in San Antonio what keeps the city's lights on and the answer comes in institutions: the Army and the Air Force, the hospitals, the insurer, the grocer, the visitors walking the River Walk. Nobody says "the truck plant." Yet out past the last of the South Side neighborhoods, on a patch of ground big enough to hold a small town, a factory has been turning out full-size pickups since 2006. It arrived within a few years of the closing of Kelly Air Force Base, and it proved that the South Side could land a different kind of employer than the one it had lost.
The dates are firm. The Texas State Historical Association's history of San Antonio records a groundbreaking for a Toyota assembly plant in 2003 and counts it among the city's notable business gains of those years. The company's own history, as summarized in a standard reference, pins the day to October 17, 2003, and has the first new trucks rolling off the line in November 2006.
How Texas won the site
In 2002, Toyota looked at sites in five states for a plant to build the second generation of its full-size Tundra pickup. Texas took it after offering $227 million in subsidies. That figure says plenty. A company choosing among states can ask each one to carry part of the cost of a plant, and each one has reason to say yes: construction work, permanent jobs, years of local spending.
The deal had critics then, as such deals do, and both sides had a case. Supporters argued that an assembly plant is the sort of anchor that pulls in parts suppliers and training programs, so the payoff lies mostly in what grows around it. Skeptics argued that subsidies reward a company for a choice it might have made anyway, and that the money comes out of schools and services. What can be cited is the amount and the outcome. How the cost divided between state and local hands is not part of the public record cited here, and guessing at it would be worse than leaving it blank.
The timing was particular. The 1995 base-closure round recommended shutting Kelly and Brooks. Kelly Air Force Base was inactivated on July 13, 2001, and the property reopened as Port San Antonio in 2007. Brooks Air Force Base closed on September 15, 2011. That conversion is told in From Kelly Field to Port San Antonio and The 1995 base-closure fight over Kelly and Brooks. For the South Side the dates meant an odd stretch: one very large federal employer winding down while a very large private one went up.
What went up
The plant sits on 2,000 acres of the far South Side, with an assembly building of about 2 million square feet. Toyota planned an initial capacity of 150,000 vehicles a year, later raised to 200,000, and its investment in the plant reached $1.2 billion.
Planners made a point of the supply base. Suppliers were built on the site and ship directly to the factory. The practice, sometimes called co-location, cuts transport costs and delays on a line that needs the right part in the right order at the right moment. It also changes what a plant means to the people nearby, because the jobs are not only on the Toyota payroll but in the supplier buildings alongside it. Which suppliers are there, and how many people they employ, changes over time and is the plant's to publish.
The sequence of assembly, in the generic sense, runs like this. Stamped body parts are welded into a body. The body is painted. The painted body meets the frame, the engine and the interior on the final line. With the supply base next door, each hand-off is shorter.
The first years
The first new Tundras came off the line in November 2006 at a grand-opening event. One Toyota executive called the launch the "single biggest and most important launch" in the company's 50-year U.S. history, according to the plant's published history. The Tundra was the company's bid for the large-truck segment, long held by American manufacturers.
Those early years did not run in a straight line.
- Sales of the 2007 Tundra nearly sold out the plant's 200,000-unit annual output.
- Sales slumped in 2008, and Toyota paused production for three months.
- In 2008 the company moved all Tundra production to San Antonio, which the plant's history says preserved 1,850 jobs.
- Sales were just under 140,000 Tundras in 2009.
- After a California plant stopped building the Corolla and the Tacoma in 2009, the San Antonio plant added 1,000 workers to build the Tacoma.
A factory this size feels the business cycle in a way a headquarters does not. When demand falls, the line can stop, and when a sister plant closes, work can land somewhere else. Both happened within three years of opening day.
The plant now
The newest figure in the reference summary is an employment count of 3,200 in 2022. The Sequoia, a large SUV, began production that year on the same frame as the Tundra. The Tacoma is less settled. The reference page says Tacoma production at the plant ended in 2020 to 2021 as output shifted to Guanajuato, Mexico, while a footnote cites a 2026 report of a $3.6 billion Toyota investment to move Tacoma production from Mexico to Texas. Those two accounts do not agree, and which one holds today is Toyota's to say. Anyone who needs the current list of models built here should look to the company's own announcements.
The back-and-forth is a lesson in itself about manufacturing in a trade-linked region. Which factory builds which model is decided at corporate headquarters, on a timescale of years, in answer to tariffs, demand and cost. San Antonio sits on the highway corridor that ties Texas to the border; the topic pages on freight and the border corridor cover the wider picture, and Laredo and the border towns of Eagle Pass and Del Rio explains why the road to Laredo matters to the city.
A small slice of a big economy
Other sectors dominate the employer rolls. The Texas Comptroller's 2025 study of military installations counts 74,713 direct employees at Joint Base San Antonio, with output of about $53.5 billion. Valero Energy and USAA, both Fortune 500, are headquartered here, along with the grocer H-E-B, and the city's economy leans hard on health care, government, professional services, oil and gas and tourism. Against that lineup, a single assembly plant with several thousand workers is a big employer but not the center of gravity.
Its weight is of a different kind. This is a production employer in an economy of offices, bases and hospitals, and one of the few places where the city's fortunes are tied straight to global supply chains. Both points fit the larger story in Joint Base San Antonio by the numbers, where military employment sets the baseline, and in USAA, Valero and Frost: three headquarters, where the headquarters economy sits.
"The South Side" covers a lot of ground, in the city's planning documents and in neighborhood talk alike: the missions in the north, Harlandale and Palm Heights, McCreless Meadows, the Brooks redevelopment and, farther out, the country where the plant stands. Brooks covers the former Brooks Air Force Base redevelopment, and The Mission District covers the missions strip along the river. They are different corners of one side of town, and they share a history of federal and industrial paychecks.
Where the workers come from
A plant draws its workforce from schools and colleges as well as from other plants. The South Side has the Alamo Colleges District, which runs five colleges across the city, and a standalone university, Texas A&M University-San Antonio, described in Texas A&M University-San Antonio: from branch to standalone in 2008. No formal training agreement between any of them and Toyota is claimed here. What can be said is that the region's technical education sits in the same part of the county as the plant.
What a plant means next door
A factory with thousands of workers touches the land around it in ways that are easy to list and hard to measure. There is the payroll. There are the supplier buildings next door, the trucks on the roads, and the demand for housing, schools and services within a commute of the gates. The plant's size and employment are known; its effect on any one neighborhood is harder to pin down, so those effects are described and not counted.
Scale is something the record does allow. The plant's 3,200 employees in 2022 are a small share of the 74,713 direct employees at Joint Base San Antonio in 2025, yet the two numbers describe very different kinds of work. One is a military and training workforce spread across several installations; the other is a single production site. Each answers to decisions made far from San Antonio, by the Defense Department in one case and a corporate headquarters in the other, a theme that recurs in the city's economic history.
Quick answers
When did the plant open? Ground was broken in 2003 (October 17 in the plant's own history), and the first new Tundras were built in November 2006.
How big is it? The site covers 2,000 acres and the assembly plant is about 2 million square feet.
How much did Toyota invest? The reference summary gives $1.2 billion.
Where is it? On the far South Side of San Antonio, well outside the downtown core.
What does it build? The Tundra since 2006 and the Sequoia since 2022; see the note above on the Tacoma.
How many people work there? 3,200 as of 2022, per the reference summary. A current figure is a question for the company.
San Antonio's economic history reads as a chain of anchors. The Spanish presidio and missions gave way to military posts, the posts to bases, and the bases, as they closed, to a mix of redevelopment and new industry. The truck plant is one product of that last turn.