The new terminal at San Antonio International: cost, gates and 2028

A roughly $1.2 billion terminal broke ground in December 2024 with 18 gates and a 2028 target.

Anyone who has circled the lot at SAT on a Friday afternoon knows the airport has two terminals. By 2028 it is supposed to have three. The airport sits about eight miles north of downtown and answers to the city's Aviation Department, which is running what it calls the Terminal Development Program. The centerpiece is a new terminal with 18 gates, one security checkpoint and, by the city's schedule as reported, a 2028 opening. The price is usually given as $1.2 billion. Some reports say $1.4 billion. Why a reader will see both numbers is a good part of the story.

What is going up

Ground broke in December 2024. The building, which news coverage calls Terminal C, runs about 850,000 square feet and carries about 40,000 square feet of concessions space behind a single security checkpoint. A 3,000-space garage and ground transportation center, with ticketless entry and reserved spots, is due in late 2027, ahead of the terminal itself. Drivers get the new front door first.

The gate count moved along the way. The plan called for 17 gates, and in December 2025 an 18th was added. Coverage of the change says the project is still on track for 2028 and says little about what the extra gate buys. It buys something. Gates cap how many aircraft can sit at the terminal at once, and each one is a place where an airline can base a plane or turn one around. Gates are also costly, so adding one in the middle of a design is not a small decision.

The two terminals already in use are getting money, too. Local news coverage put $200 million toward Terminal A and $100 million toward upgrades at Terminal B, and a "ground-load expansion" at Terminal A has opened. Those are news-coverage figures. The Aviation Department's own site, flysanantonio.com, is the place to confirm them, and the place to find addresses, phone numbers and the day's flight information.

$1.2 billion or $1.4 billion

Cost is the number people ask about first, and the answer depends on what gets counted.

  • $1.2 billion is the figure for the Terminal Development Program in the December 2025 report, and the figure used at the groundbreaking.
  • $1.4 billion turns up in other coverage, with no explanation of the gap.

Gaps like this have ordinary causes. A program can fold in or leave out a parking structure, roadways, utilities, the baggage system, contingency money, or the work on the older terminals. A figure quoted at groundbreaking may be a budget, while a later one may carry added scope, the 18th gate for one. Construction costs also climb between the year a budget is set and the year the money is spent. The sensible reading is that $1.2 billion is the number tied to the project as announced and $1.4 billion is a higher figure that may reflect a wider definition. Anyone who has to cite one should cite the one in the airport's own documents and say which it is.

Some arithmetic on scale. A terminal of about 850,000 square feet against a $1.2 billion program works out to about $1,400 per square foot ($1.2 billion divided by 850,000). That is a rough comparison, since the $1.2 billion covers more than the building, and it is not a construction bid. Still, it shows why an airport terminal is nothing like a house or an office tower per square foot: it holds security, baggage, apron, utilities and concessions all at once.

Why build now

Airports expand when they expect crowds. The figures reported in December 2025 show the reasoning, and they do not all point the same way.

  • A December 2025 projection put 2025 traffic at 11.41 million passengers.
  • A February 2026 news report said the airport ended 2025 at about 10.7 million, down 3.2 percent from 2024, its busiest year, when it passed 11 million.
  • The airport had 49 nonstop destinations by the end of 2025, up from 34 or 35 before the pandemic, with five new routes added that year and a 50th in the works. Air Canada announced nonstop service to Toronto for May 2026.
  • The airport's economic impact was put at $7.4 billion a year and 55,000 jobs, and the new terminal is expected to add 16,000 permanent jobs.

A December projection is a forecast. A February count is a result. The forecast of 11.41 million and the result of about 10.7 million differ by about 0.7 million, or about 6 percent ($0.71 million divided by 11.41 million). A 3.2 percent slide from a bit over 11 million to 10.7 million is a small dip in a growing system, and it did not stop a single crane. That fits how airports plan: they build for a decade of demand, not one year's. The case for the terminal says the existing two are too small and too old for the long run. The case against, which gets made about any big airport project, says a year of falling traffic proves demand is not guaranteed. Both are fair arguments, and how the airport weighs them is not spelled out in the reporting.

How the project is paid for is also unsettled in the coverage. The December 2025 report names only the $1.2 billion program, and its web address hints at federal money without the article detailing the sources. Anyone who wants the funding mix should look to the city's capital budget and the airport's documents, and How to read the San Antonio city budget explains how to read them.

The passenger numbers, in perspective

A few conversions make the traffic figures easier to picture. A year of about 10.7 million passengers is about 29,300 a day (10.7 million divided by 365), counting people boarding and people getting off. The reported $7.4 billion in economic impact and 55,000 jobs implies about $135,000 of impact per job (7.4 billion divided by 55,000). That tells you how the airport's number is built. It is not a wage. Destinations grew from 34 or 35 before the pandemic to 49 by the end of 2025, an increase of 14 or 15 cities, about 40 percent, and every new route is an airline betting that people will fill the seats.

The 16,000 permanent jobs expected from the new terminal is a projection, and the count is an estimate of impact. Economic-impact figures usually include indirect jobs, the suppliers and the restaurants that feed airport workers, along with the jobs at the airport itself. Treat the figure as impact, not as the airport's payroll.

What it means for the ride to the airport

The practical question is what any of this does to the person flying out of San Antonio today.

  1. Terminals A and B are still the airport. Until the new terminal opens in 2028 they are where travelers check in and board, and their upgrades are underway.
  2. The garage comes first. The 3,000-space garage and ground transportation center is scheduled for late 2027, well before the terminal. Parking and pickup will change before the check-in hall does.
  3. Ground transportation is its own question. The routes from the airport to downtown are laid out in Getting from San Antonio International Airport to downtown. The Green Line, which runs from the area near the airport down San Pedro Avenue to the missions, is a future piece of that answer, and VIA's own page puts its opening in 2028 too. The two projects keep similar clocks. That is a coincidence of timing, not a coordinated plan, as far as anyone has said. The Green Line is covered in The Silver Line and what comes after the Green Line.
  4. The old terminals' fate. Nothing reported says what becomes of the existing terminals once the new one opens. The $200 million and $100 million upgrades suggest they stay in service.

For a traveler's guide to what each terminal handles today, see A passenger's guide to San Antonio International's two terminals. For the record 2024 and what followed in 2025, see airport traffic: the 2024 record and the 2025 dip. San Antonio also owns a second airport, Stinson Municipal, for general aviation, described in Stinson Municipal Airport: the city's other airfield.

Who is watching

The airport is a city department. The Aviation Department runs both airports, the City Council approves the big contracts, and the Federal Aviation Administration posts flight-delay information at nasstatus.faa.gov, which the city's resource list links. Council meetings are open to the public, and anyone can register to speak, as described in How to speak at a San Antonio City Council meeting. For contact details, go to the airport's own website. The agency page is San Antonio International Airport.

What could move the numbers

A project like this is a bet on years of growth, and four things could shift the figures before 2028.

  • Cost. If the final bill nears $1.4 billion, the difference is about $200 million, the same as the reported Terminal A upgrade program.
  • Schedule. The terminal is on track for 2028, according to the December 2025 report. Big projects slip. The Missions' ballpark, covered in What happens to Nelson Wolff Stadium, is a local example of a date that moved by a year.
  • Traffic. Whether the airport returns to growth after 2025's 3.2 percent dip is the open question under the whole investment.
  • Routes. More nonstop destinations, such as the 50th the airport said was in the works, strengthen the case for more gates.

The numbers say it plainly enough: 18 gates, about 850,000 square feet, a garage first and a terminal in 2028, for a price reported as $1.2 billion and sometimes $1.4 billion. When a new figure shows up, ask first what it counts.