The five-level 1604 and I-10 interchange and its eight flyovers
How TxDOT is rebuilding the Loop 1604 and I-10 junction on the Northwest Side into a five-level interchange with eight flyover ramps.
The ramps went up one at a time. The first opened in December 2024. Three more followed in the summer and early fall of 2025, two opened together in November 2025, and one was left. By the schedule the Texas Department of Transportation (TxDOT) announced, the eighth and final flyover ramp at the Loop 1604 and I-10 interchange was to open by 5 a.m. on February 5, 2026. Behind those dates is a rebuilt junction where two of the region's biggest roads meet on the Northwest Side, near La Cantera and The Dominion, where a large share of the city's growth has been squeezing through for years.
This is a case study of one piece of the Loop 1604 North Expansion: what the interchange is, how it is layered, when the ramps opened and what is left to do.
Why this junction
San Antonio is ringed by two loops. Loop 410 runs about 53 miles around the older city, and Loop 1604, about 96 miles, is the outer ring through the growing suburbs. The interstates cross both, and the spot where Loop 1604 meets I-10 on the Northwest Side is among the busiest meeting places on the outer ring. The corner sits close to the commercial and entertainment area known as La Cantera and the prestigious Dominion neighborhood, described in La Cantera and The Dominion: a quarry that became a resort district and La Cantera and The Dominion, and to the South Texas Medical Center area, described in The Medical Center.
How the junction was laid out before is left alone here. What matters is what replaced it: a stack in which the two highways cross on separate levels and the movements between them pass over everything else on ramps.
Five levels
TxDOT's description of the finished interchange, as local coverage reported it, has five levels.
| Level | What it holds |
|---|---|
| 1 (ground) | Roundabouts that give access to adjacent properties, new turnarounds and sidewalks along I-10, and the existing VIA Park and Ride, modified to fit underneath |
| 2 | The I-10 main lanes, with space reserved for future I-10 expansion, plus new collector-distributor roads that let local traffic bypass the roundabouts |
| 3 | The Loop 1604 main lanes, expanded with an additional main lane and an HOV lane in each direction, an 18.5-foot vertical clearance for large trucks, and collector-distributor roads on the outside |
| 4 and 5 | The eight flyover ramps, which carry higher-speed connections between Loop 1604 and I-10 |
The idea of the stack is simple even if the concrete is not. A driver who wants to stay on the highway they are on stays on levels 2 or 3. A driver who wants to switch highways takes a ramp on levels 4 or 5, a direct connection with no stopping. A local driver headed for a store or a house on the ground uses level 1 or the collector-distributor roads. By sorting those three kinds of trips onto different levels, the design tries to keep each out of the others' way.
Eight ramps is, by count, the full set of turns between two crossing highways. Two highways cross, each with two directions, and a driver on any of the four approaches can go onto either direction of the other highway. Four approaches times two turning options is eight turning movements, and the interchange gives each a flyover. The numbers add up neatly, the sign of a full direct-connect design rather than one where some turns use slower ramps or ground-level streets.
When the ramps opened
Local coverage lists the sequence. Seven were open before the final ramp, with two opened together in November 2025.
| Opened | Movement |
|---|---|
| December 2024 | Eastbound Loop 1604 to westbound I-10 |
| Early June 2025 | Westbound I-10 to westbound Loop 1604 |
| August 2025 | Westbound Loop 1604 to eastbound I-10 |
| September 2025 | Eastbound Loop 1604 to eastbound I-10 |
| October 2025 | Westbound I-10 to eastbound Loop 1604 |
| November 2025 | Eastbound I-10 to both directions of Loop 1604 (two ramps) |
| By 5 a.m., February 5, 2026 (scheduled) | The eighth and final ramp, reached on Loop 1604 just past Lockhill Selma Road, entering the westbound I-10 main lanes past La Cantera Parkway |
Count the rows: one, one, one, one, one, two, one. That makes eight. The announcement of the final ramp did not name its movement, but by elimination the remaining turn is westbound Loop 1604 to westbound I-10, which fits the description of how drivers reach it. That last movement is deduced from the list, not stated by TxDOT.
A note on dates. Some coverage of the project gave different completion targets for the last ramp, including the end of 2026. The TxDOT announcement reported in local coverage names February 5, 2026 as the date by which the ramp would open. Whether it opened on that date should be confirmed on TxDOT's and DriveTexas's pages, which carry the current status. When that coverage appeared, the interchange as a whole was about 70 percent complete, and TxDOT's estimate for finishing it was 2027.
What is left
The last ramp does not finish the project. The ramps are the most visible part, but the lower levels, the roundabouts, the turnarounds and the sidewalks were still under construction. The completion estimate for the interchange was 2027.
It also sits inside a larger program. The Loop 1604 North Expansion is a series of segments. Segment 3, between I-10 and US 281, was estimated complete in 2026 at a cost of $279 million. Segment 4, from US 281 to Redland Road, has been under construction since April 2024, with completion expected in 2027. The pieces are being built in sequence, and the corridor will not behave like a finished road until all of them are done. The segment-by-segment details are in The Loop 1604 North Expansion, segment by segment, and the larger rings are in Two rings: Loop 410 and Loop 1604.
What a flyover costs and buys
Flyover interchanges are among the most expensive things a highway department builds. No cost for this interchange is given here, and none is guessed. What the record does give is a set of design choices that show what the money was buying.
- Vertical clearance. The Loop 1604 level has an 18.5-foot clearance for large trucks. That matters on a corridor that carries freight, and it is a reminder that these loops serve trucks as well as commuters.
- Room to grow. The I-10 level includes space reserved for future expansion of I-10. Building the structure now with room for lanes later avoids rebuilding it.
- High-occupancy lanes. The Loop 1604 expansion adds an HOV lane in each direction, along with an additional main lane.
- Ground-level access. The roundabouts and turnarounds on level 1 serve adjacent properties, so businesses and homes at the junction are not cut off.
- Transit. The VIA Park and Ride was modified to fit underneath the structure, so a bus rider's connection survives the rebuild.
Supporters of such projects argue that grade-separated, direct connections cut the stop-and-go that causes congestion and crashes at signalized interchanges, and that a regional loop has to carry suburban growth. Critics argue that more lanes can induce more driving, do little for people without cars, and that the money could go to transit. San Antonio's own transit plans, such as the Green Line in The Silver Line and what comes after the Green Line, answer the second argument; the loop work answers the first. The two are being built at once, paid for through different agencies, and a resident can reasonably hold both views.
For drivers
Some practical points follow, and and most of them come down to looking before you leave the driveway, not after you are stuck in the merge.
- Check conditions before you go. TxDOT's DriveTexas site, drivetexas.org, shows closures and construction, and the TxDOT San Antonio District answers questions at 210-615-1110. The page is described in How to check DriveTexas before a San Antonio drive.
- Expect change. With the lower levels still being built, ground-level lane shifts and ramp closures are likely for some time, though no schedule for them is published here.
- Know your ramp. The list above shows when each movement opened. If you use an older route out of habit, the flyover for your turn probably exists now.
- The interstates beyond. The I-35 corridor from Loop 410 North to FM 3009 is a separate 2022 to 2027 project, so the region's roads are under construction in several places at once.
Why it matters past the northwest
An interchange at the edge of town touches the whole city, because the loops tie the metropolitan area together. A trip from the far northwest to the airport or the northeast runs on Loop 1604 and its junctions, and freight bound for the interstates uses the same ring. A metropolitan area is only as fast as its worst junctions, and the Loop 1604 and I-10 meeting has been one of them. Residents will judge the project by whether the trip between the Medical Center area, La Cantera and the suburbs gets easier. That can be measured only after the work is done and traffic has settled, and it is one of the numbers worth watching in 2027. For the city's neighborhood-level picture, see A neighborhood overview of San Antonio, and for the county government that shares in regional transportation decisions, see the Bexar County government record.